Project Details

Category: Government / Education
Client: Department of Finance – Building Management and Works WA
Location: Aulberry Parade, Leeming WA
Contract Value: $1,230,000 + GST
Architect: M&S Matthews & Scavalli Architecs – Sally Matthews

Overview

The administration block has been built as the offices for many of the school staff. The administration block features a reception area, interview room, therapy room, meeting room, first aid, lunchroom and several staff offices.

Prominent features

The building has two long passageways with high curved ceilings, along with several storerooms and toilets. Bisschops pre-finished cladding to the window boxes and to the high-level windows, and high curved ceilings in passageways with high windows that emphasise reflecting natural light into the building.

Colorbond roof with bisschops CFC prefinished cladding feature; double brick walls externally with stud walls internally; implementation of Structural Steel columns and roofing, and installation of metal doors, windows and specified glazing.

Project Challenges

Working within existing school premises meant identifying busy school periods and ensuing traffic. Traffic management procedures implemented throughout works.

As organised with the client, deliveries were restricted during peak school traffic periods (beginning and end of day) to minimise impact on the public and school processes. Also, stringent site access protocol including police clearances, principal and agent induction procedures and regular toolbox meetings, and secure temporary fencing and hoarding were implemented throughout the duration of works.

Limited by the size of access roads therefore no trucks larger than “6 wheelers” were allowed onto site without at least 3 working days’ notice to the school